Case study · Geotube
Kuantan Maritime Hub
Client
Muhibbah Engineering
Location
Sungai Karang, Kuantan, Pahang
Period
2022–2026
Scope
Geotube, geotextile, silt curtain, geobag
The project
The challenge
Kuantan Maritime Hub is a 500-acre development at Sungai Karang, next to Kuantan Port in Pahang, including a section for the Royal Malaysian Navy.
Building the platform out over the shoreline needs containment bunds to hold the fill, and measures to control turbidity in the surrounding water while the work goes on.
Our role
What we delivered
For Muhibbah Engineering we have supplied and installed geotubes and related works across several phases since 2022:
- Phase 1 (from 2022): geotubes, geotextile and silt curtains, including the Royal Malaysian Navy section
- Phase 2, Zones 1 and 2 (2024–2025): geotubes, geobags, geotextile and silt curtains
- Further Phase 1 geotube packages under way in 2026
Have a similar project?
Talk to the team that delivered Kuantan Maritime Hub. We'll come back with a method, a programme and a price.