T: 1700-81-9753 info@ajtgeo.com
AJT GeosyntheticsGround Engineering · Since 1994
Case study · Aviation

KLIA2 & LCCT

Client

WCT · Suhati · Gadang

Location

Sepang, Selangor

Period

2009–2013

Scope

PVD, woven & non-woven geotextile

The project

The challenge

KLIA2 is the low-cost carrier terminal of Kuala Lumpur International Airport at Sepang. It opened in 2014, replacing the earlier LCCT. Terminals, aprons and runways need firm, predictable ground, so soft areas had to be treated before construction.

The works were split into multiple packages, covering the terminal development, airside areas, runway and perimeter roads, each delivered by a different main contractor.

Our role

What we delivered

Our group worked across several of these packages. For WCT we installed prefabricated vertical drains and geotextile on the KLIA2 development. For Gadang we carried out works on the LCCT runway, and for Suhati we supplied and installed geotextile for airside upgrading and the LCCT perimeter road.

  • PVD installation with our own rigs
  • Woven and non-woven geotextile supply and installation
  • Work coordinated across multiple main contractors and packages
On site

Project photos

Services used

Prefabricated Vertical DrainsGeotextiles

Have a similar project?

Talk to the team that delivered KLIA2 & LCCT. We'll come back with a method, a programme and a price.